The injection unit is the assembly that brings together the barrel, screw, injection mechanism and the moving carriage. If it is installed carelessly, alignment, drooling, unstable cushion and judder keep coming back. This article follows the installation sequence and lists the details that are easily missed, together with the re-check points.

1. Checks before installation

1.1 Match the unit to the machine and mould

Nozzle center height and unit travel have to match the fixed-platen locating ring and the mould's injection position. If the machine and mould do not correspond, there will be no adjustment margin even after installation. Check the nozzle specification, barrel configuration and shot weight first.

1.2 Guideway surface and datum condition

The guideway faces must be clean, straight and free of dents and rust. The guideway datum sets how the carriage moves and aligns; if the datum is off, the unit will stay biased no matter how it is adjusted.

1.3 Prepare lines and wiring in advance

Hydraulic hoses, cooling water lines, heater and thermocouple wiring and sensor signal lines should be laid out and labelled before the unit is set down, so they do not have to be pulled and re-routed afterwards.

2. Setting down and fixing the unit

2.1 Locate the carriage on the guideways

After the carriage rests on the guideways, align the locating datum and mounting face before fastening. Fasten in passes with even force; locking one side first can pull the carriage out of position.

2.2 Nozzle center height and level

The nozzle center height must line up with the locating ring center on the fixed platen. The level of the carriage base directly affects nozzle pitch. Rough-set the center height first, then re-check level against the guideway face.

2.3 Fastening and travel margin

After locking, confirm there is still travel margin for unit advance and return, and the limit positions do not bottom out. The lock blocks must sit against the carriage, not hang in the air.

3. Alignment and fit details

3.1 Nozzle and locating ring concentricity

The nozzle axis must be concentric with the locating ring center; check the offset in left/right, height and pitch directions separately. This connects to the alignment work done in running, but the datum has to be right at the installation stage first.

3.2 Screw-barrel fit and check ring

Screw-to-barrel clearance meets the assembly requirement; the check ring and non-return tip turn freely without binding. Heater bands and thermocouples seat properly against the barrel.

3.3 Guideway clearance and free movement

Carriage-to-guideway clearance is even; manual or low-speed advance and return show no binding or local resistance. The lubrication passages are open and the lubrication points are covered.

4. Lines, temperature control and electrics

4.1 Hydraulic hoses and return oil

Hose routing must avoid rubbing moving parts; connections follow labels and return oil flows freely. After hoses are fixed, cycle the unit to confirm they are neither pulled nor interfering.

4.2 Barrel cooling and heater wiring

Cooling water in and out are correct with no leakage; heater wiring and thermocouples match one to one, without reversed or mixed lines.

4.3 Sensors and limits

Unit advance/return limits and pressure or position sensors are firmly mounted, and their trigger positions are correct. Wire numbers are labelled clearly for later troubleshooting.

5. Trial movement and re-check

5.1 Dry-cycle advance/return and judder check

Run low-speed dry cycles back and forth; watch whether the carriage moves smoothly, with no judder or noise, and whether the end position repeats consistently.

5.2 Hot-state alignment re-check

After heating reaches set temperature, re-check nozzle alignment once more; cold and hot states differ. Lock only after the hot-state re-check.

5.3 Cushion and injection stability

After trial shots, watch whether the cushion is stable, the nozzle does not drool, and part weight repeats. If anything is off, trace it back to installation and alignment first.

6. How Konger configures the injection unit

Ningbo Konger Machinery Co., Ltd. is based in Ningbo, founded in 2013, and covers the development, manufacture, sales and service of injection molding machines. The range is built around the K-TEC servo energy-saving series, with CMS (Color Mixing System) two-colour and sandwich machines, close to thirty customised dedicated models.

  • Guideway and carriage built as a unit. Datum faces are controlled at the assembly stage, reducing repeated adjustment after installation.

  • Screw and barrel matched to the material. Fit clearance and check ring are checked at the factory; rotation is free without binding.

  • Unit motion tuned with the whole machine. Advance/return and pressure signals are verified together, and commissioning parameters can be stored and recalled.

  • Dedicated models configured to the part. Unit travel and shot weight are set to the product, so installation margin fits the mould more closely.

7. Installation detail checklist

  1. Does the nozzle center height match the locating ring?

  2. Is the guideway surface clean and straight?

  3. Is fastening done in passes without pulling the carriage off position?

  4. Is there travel margin for unit advance and return?

  5. Are nozzle left/right, height and pitch checked separately?

  6. Are screw-barrel fit and check ring free and flexible?

  7. Do hoses and water lines match their labels without pulling?

  8. Is alignment re-checked hot before locking?

Conclusion

The key to injection-unit installation is getting datum, alignment, fit and lines right when the unit is set down, instead of leaving them for repeated tuning at the trial-shot stage. When these details are handled properly, the unit has a base for steady running and consistent parts.